Columbia Heights is hiring a new contractor to finish its 2025 concrete alley construction project after the original contractor ceased operations before completing the work.
The Columbia Heights City Council voted unanimously Oct. 26 to award a $148,850 contract to Goodmanson Construction to complete the remaining work.
The original $1,072,501 contract was awarded to Equity Builders & Construction Services of Rosemount, which hired Goodmanson as a subcontractor to perform much of the work.
Equity subsequently ceased operations and was barred from further government contracting, Assistant City Engineer Kelly Monahan wrote in a staff report.
On Feb. 13, Old Republic Surety Company, which issued Equity’s performance bond, directed the city to freeze payments to the contractor.
By that time, the city had paid Equity $804,389.97. Another $145,344.12 in payments was frozen, while $41,045.79 was withheld for warranty claims.
City Engineer Rochelle Widmer notified Equity July 23 of outstanding work and construction deficiencies, but the company did not respond by the July 27 deadline.
City Attorney Scott Lepak notified Old Republic Sept. 21 that the city was considering declaring the contractor in default. The city had received no response as of Oct. 21.
The new contract will be funded through the remaining money from Equity’s original contract, with additional costs covered by the performance bond if necessary.
Council Member Rachel James said drainage problems and cracks affect residents throughout the city and thanked staff for working to resolve the issues before freezing weather arrives.
Mayor Amada Márquez Simula said she was relieved the city was moving toward completing the project after a lengthy process.
“So I’m glad we are able to push through and not have to go further than one year on this,” Márquez Simula said.