The Blaine City Council unanimously approved final assessments for the 2024 Southwest Area Street Reconstruction project Sept. 21 despite concerns from a local nonprofit that the charges could affect its educational programs.
Mohammed Gulam, a board member of the Darul Arquam Center of Excellence, told the council the nonprofit was concerned about the financial impact of its two assessments totaling $14,228.
The center provides educational services in math, science and Quranic studies. Gulam described it as a lean organization with limited financial resources.
Director of Engineering Daniel Schluender said the project included improvements along 89th Avenue from University Avenue to Highway 65, 85th Avenue west of Lincoln Street to Central Avenue Service Road, and Lincoln Street between 85th and 89th avenues.
Other project areas included 85th Avenue from Lincoln Street to Highway 65 and Central Avenue from 87th Avenue to the cul-de-sac south of 89th Avenue.
The project’s feasibility report estimated the total cost at $8.5 million, with approximately $1 million to be covered through assessments.
The city’s public utility fund will contribute approximately $2 million for water, sanitary sewer and trunk stormwater improvements. The Pavement Management Program fund will contribute approximately $3.2 million, while state aid funding will cover another $1.7 million, Schluender said.
Two property owners along 89th Avenue requested assessment deferrals.
Gulam said the center had been notified about the project but was concerned about the effect of the assessments on its operations.
“With this, we are assessed two assessments of $13,700 and $528,” Gulam said. “This amount is huge for a small business like ours, and would limit our ability to perform duties that we are doing for the community for the children.”
Gulam asked whether the project could be canceled or, alternatively, whether the city could remove the assessments from the center’s property taxes, along with those of other residents and businesses.
Schluender explained that the city’s assessment policy considers the types of land use benefiting from street improvements. He also noted that construction was complete and the improvements had already been made.
In response to Council Member Tom Newland, Schluender said the center would have 15 years to repay its assessments.
He also explained that the property received two separate assessments because it is a corner lot. Under the city’s assessment policy, a corner lot receives a credit for 150 feet of street frontage along its longer side.
“In this case…one of those sides did receive a 150 foot credit and did not pay for the entire corner lot,” Schluender said.
Council Member Chris Massoglia said the city previously explored exempting nonprofits from its assessment policy after a church faced an assessment of between $60,000 and $70,000 for work along a frontage road.
Massoglia said the city was unable to change its policy at the time because of state requirements governing how assessments are applied.
“We have looked into that in the past, and I don’t think unfortunately there’s anything we can do for nonprofit organizations,” Massoglia said.
The Blaine City Council also unanimously approved a city code amendment allowing new billboards on properties designated for airport land use.
Community Development Director Sheila Sellman said the amendment was initiated by the Metropolitan Airports Commission. Existing billboard standards will remain unchanged, and any proposed billboard will be subject to the city’s permitting process.
Council Member Tom Newland expressed concern about the proposed location near County Road J, south of the airport’s north-south runway, saying he would be hesitant to consider a height variance.