Homes near National Street and 114th Avenue with private wells contaminated by 1,4-dioxane will be connected to Blaine’s municipal water system through a roughly $1.1 million state-funded project.
The Blaine City Council unanimously accepted a just more than $1 million bid from Castrejon for phase two of the National Street Water Service Project at its Sept. 21 meeting. With a 10% contingency, the construction budget is approximately $1.1 million.
Engineering Director Daniel Schluender said the Minnesota Pollution Control Agency has monitored groundwater in the area because of contamination linked to the former Johnson Brothers landfill, located in what is now Lochness Park. Testing found 1,4-dioxane in private wells serving nearby homes.
The MPCA completed an initial project in 2023 that connected two properties on the south end of National Street to the city’s water system.
“They did a project in 2023,” Schluender said. “The two properties on the south end of National Street were connected to city municipal water.”
The agency later addressed contamination at the remaining affected properties on National Street and 114th Avenue by either connecting them to municipal water or installing filtration systems inside the homes.
Phase two will extend the water main to the remaining properties and connect them to the municipal system. The existing private wells will be sealed. The work will also add a hydrant to the city’s water system.
The MPCA obtained grant funding for the project and asked Blaine to administer the work because the city has more experience with municipal construction and contracting, Schluender said. Blaine will hold the construction contract, pay the contractor and seek reimbursement through the MPCA grant.
Council Member Leslie Larson said residents became concerned when contamination was discovered at the first two properties and those homes were connected to city water.
“If they’re contaminated, are we contaminated, too?” Larson recalled residents asking.
Larson said she spent a day knocking on doors with an MPCA employee to answer residents’ questions and explain why two of their neighbors were receiving municipal water connections while other property owners would have had to pay for their own.
Providing clean water to the rest of the area would have been costly, and the city did not have a funding source at the time to connect the remaining homes, Larson said.
Council Member Newland noted that Castrejon is a Blaine-based company.
“Good to see our state tax dollars coming back into the community, going to a local business as well,” Council Member Sanders said. “Helping residents sounds like a good win.”
The council also unanimously approved a contract with Short Elliott Hendrickson for construction administration and observation services.
SEH proposed providing the services for $113,000, Schluender said. With a contingency included, that portion of the project has a $124,000 budget and will also be paid for with MPCA grant funds.